Waukegan Washington Street Pace Route Access Improvements
This project will add multi-modal access improvements to multiple Pace Routes on the Washington Street corridor. Route 572 is the primary route that serves the corridor, although Route 562 also serves portions of the corridor and four others connect to it (561, 565, 566, 569). Improvements include bus shelters and concrete pads, wayfinding to important destinations, curb extensions at the intersection with the Robert McClory Bike Path, crosswalk improvements along the project area, and bike parking at the Metra station.
Waukegan is moving forward with the Section 1440 engineering process in order to reduce the time the engineering process will take. They have submitted a Project Program Information form to IDOT and are awaiting approval.
| Source | Amount |
|---|---|
|
RTA |
$13044.00 |
|
Local |
$39132.00 |
|
Federal |
$208704.00 |