Regional Capital Program

Capital programming is a core function of the RTA. RTA and the Service Boards have worked to articulate as well as advance a capital strategy for transit projects in the Chicagoland region.

Priority Projects have been identified by the Service Boards. These priority projects are updated on an annual basis. This page shows details about the funding for each priority project.

The 2025-2029 5-Year Regional Capital Program includes over 250 projects that are advancing many of these Priority Projects. The capital projects are shown in the table below, organized by Priority Project and can also be seen in a mapped form on the RTA Capital Projects Dashboard. Each project listing shows the amount of funding programmed in the 2025-2029 Regional Capital Program. Beginning with the 2025-2029 Capital Program, projects are evaluated based on 15 measures which were identified in the new Regional Transit Strategic Plan, Transit is the Answer. All projects in the 2025-2029 program show the detailed evaluations in this site.

The metrics include evaluations of Equity and Accessibility which are used in the performance-based allocation process. The region has committed to dedicating 20% of programmed funds to projects that fulfill the regional goals of improving equity and accessibility for 2025 and beyond as a part of the new performance-based capital allocation process

The Service Boards have met and exceeded the 20% goal for the 2025-2029 budget years.

Detailed analysis of the capital evaluation metrics is included in the Regional Transit Operating Budget and Capital Program

Read more about RTA’s capital programming activities here.

Project Management Oversite (PMO) data is provided for projects that are being actively monitored by the PMO group. Data included current activities, start and end date and budget and schedule status. The following page has a full list of active PMO projects.

Toggle Agency Priority Project Mode 2025 Funding 2025-2029 Funding 10 Year Funding Needed 10 Year Unfunded Need
+ Metra Administration - Metra Rail $41,946,233 $147,691,542 $382,144,040 $234,452,498

Metra's administrative projects.

Toggle Project Title Asset Category Mode 2025 Funding 2025-2029 Funding PMO
+ Capital Delivery Support Contracts Contingencies and Administration Rail $2,650,000 $7,650,000 ✔︎

Project Details

Description
The Site Surveying & Data Evaluation Services contract is intended to aid the Capital Delivery Department when surveying, initial site data collection, project closeout checks, or other similar type of work is requested for a new area, a new potential project is requested, or when new information arises in existing projects. Site surveys and data evaluation that will be provided by this contract will help to inform the Capital Delivery Department of the up-to-date information that is required for accurate cost estimating, accurate scoping, and improvements to project delivery. This funding also help streamline design engineering and NEPA compliance.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $1,825,000 $5,000,000 $6,825,000
State $0 $825,000 $0 $825,000
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $2,275,000 $2,650,000 $5,000,000 $9,925,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$1,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Permit expeditor services continued during this reporting. Similarly, NEPA and surveying services continued during this reporting period. A contract was awarded for on-call land survey consulting services and tasks will continue to get assigned with task orders issued for 6 stations.

Last Updated 09.12.2025

+ Contingencies Contingencies and Administration Rail $3,229,656 $8,739,948

Project Details

Description
This project will fund both emergencies and unanticipated capital needs that arise throughout the course of the program year. Items covered require immediate attention and cannot wait for inclusion in the budget for the forthcoming program year. Contingencies are necessary to fund emergency activities to prevent project and service delays.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $3,229,656 $5,510,292 $8,739,948
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $13,013,022 $3,229,656 $5,510,292 $21,752,970

Last Updated 06.12.2025

+ Financial System Replacement Contingencies and Administration Rail $0 $0 ✔︎

Project Details

Description
This project provides for the development and implementation of an Enterprise Resource Planning (ERP) System at Metra. This project will replace Metra's payroll software that is nearing technical obsolescence as Microsoft is scheduled to end support of the current application. The replacement system will integrate internal and external management of information across the Metra organization, including such areas as finance, accounting, sales, inventory, customer service and human resources.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $2,400,000 $0 $0 $2,400,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$41,754,607
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Metra was able to complete the conversion to Dynamics 365. The vendor continues to work on additional scope for post-software implementation. Metra submitted a revised procurement package for the Payroll System replacement. There were scope additions that occurred during this reporting period for the UP employees onboarding, the vendor portal, and integration with other systems. The Purchase Agreement for the Payroll System replacement was awarded and phase 1 of the project has begun in this reporting period with data requirements.

Last Updated 06.10.2025

+ Labor Apprenticeship & Development Contingencies and Administration Rail $10,202 $10,202

Project Details

Description
This project invests in Metra’s new Buildings & Bridges Apprenticeship Program. Upon conducting extensive needs assessments throughout Metra’s districts, Operations Learning & Development is requesting the resources detailed in this Capital proposal to build out an innovative, best-in-class B&B Apprenticeship program for Metra. This project will combine on-the-job training with classroom instruction, field training, simulator rooms, virtual reality training scenarios, and other best practice methods.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $10,202 $0 $10,202
Service Board / Local $0 $0 $0 $0
Total $0 $10,202 $0 $10,202

Last Updated 09.11.2025

+ Office Equipment Contingencies and Administration Rail $250,000 $1,250,000

Project Details

Description
This project consists of the purchase of various pieces of equipment, office furniture, workspaces, conference tables, break-room appliances, and small-scale climate control systems that will be utilized at Metra buildings and facilities. The current condition of the equipment that is being replaced is poor and has reached or surpassed its useful life.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $250,000 $1,000,000 $1,250,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $1,800,000 $250,000 $1,000,000 $3,050,000

Last Updated 12.19.2024

+ Procurement Oversight Contingencies and Administration Rail $0 $0

Project Details

Description
This project will provide the Mechanical Department guidance and oversight in purchasing, ensuring that Metra remains compliant with the provisions of the Federal Transit Administration's Buy America Provisions. Delays in project implementation and the need for non-Federal funding sources result from failure to comply with the Buy America provisions. Federal funding for capital projects typically includes Buy America regulations.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $800,000 $0 $0 $800,000

Last Updated 12.16.2022

+ Program Management Contingencies and Administration Rail $34,806,375 $123,441,392 ✔︎

Project Details

Description
This project will fund the professional services necessary to deliver capital projects. Project activities may include but are not limited to funding studies, concept design, developing new business tools and processes, professional services under the Project Management Oversight (PMO) contract, and the procurement of software. Historic levels of capital funding necessitate additional program management capacity.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $34,806,375 $88,635,017 $123,441,392
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $104,828,295 $34,806,375 $88,635,017 $228,269,687

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$123,877,968
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The project management oversight contract was awarded to WSP. WSP and Metra staff are working through the process to support delivery of Metra’s Capital Program. Purchase Order Releases have been approved and work is in progress on various capital projects.

Last Updated 06.10.2025

+ Project Administration Contingencies and Administration Rail $1,000,000 $5,100,000

Project Details

Description
This project funds the activities associated with the administration of capital grants and the projects in those grants. This includes only those labor, fringe and overhead costs covered by Metra’s cost allocation plan. Examples of the types of activities associated with the administration of capital grants are budget revisions, requisitions, quarterly reports and reconciliation of expenses done at project closeout. Metra funds associated with capital grant administration are recognized as capitalized costs under Generally Accepted Accounting Principles (GAAP).
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $1,000,000 $4,100,000 $5,100,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $4,700,000 $1,000,000 $4,100,000 $9,800,000

Last Updated 12.19.2024

+ Project Development Contingencies and Administration Rail $0 $1,500,000

Project Details

Description
This project will allow Metra to undertake studies to advance major capital projects and secure grant funding.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $1,500,000 $1,500,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $7,725,000 $0 $1,500,000 $9,225,000

Last Updated 12.19.2024

+ Transit Asset Management Contingencies and Administration Rail $0 $0

Project Details

Description
This project funds the continuation of Metra’s comprehensive asset assessment. This phase will consist of hiring a consultant to assist with the monitoring and implementation of Metra’s Transit Asset Management Plan as required by the Federal Transit Administration.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $3,000,000 $0 $0 $3,000,000

Last Updated 12.16.2022

+ Metra Track Improvements Rail $40,436,500 $158,536,794 $2,071,340,751 $1,912,803,957

Replace and repair track components.

Toggle Project Title Asset Category Mode 2025 Funding 2025-2029 Funding PMO
+ Catenary Structure Rehabilitation Track & Structure Rail $1,611,000 $7,391,000

Project Details

Description
This project involves the ongoing rehabilitation of various catenary structures on the Metra Electric (ME) Line including the University Park Branch, the South Chicago Branch, and the Blue Island Branch. This work typically involves refurbishing structural steel, improving walkways, replacing alternating current cross-arms, and rehabilitating concrete foundation pedestals. Specific project activities will depend on the results of condition assessments and the availability of track time to schedule work.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $1,611,000 $5,780,000 $7,391,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $5,200,000 $1,611,000 $5,780,000 $12,591,000

Last Updated 12.19.2024

+ CREATE - 75th CIP Rock Island District Connection Track & Structure Rail $6,518,000 $6,518,000 ✔︎

Project Details

Description
This project will provide engineering for the 75th Street Corridor Improvement Project (CIP) that will relieve rail congestion by separating freight and passenger rail lines in the City of Chicago. The eventual construction phases will construct a flyover to connect Metra Southwest Service (SWS) to the Rock Island (RID) Line at 73rd Street. Constructing the project will eliminate a major conflict point between Metra and freight trains, and train idling will be reduced. This funding represents Metra’s contribution to the project, other project partners within CREATE will contribute additional funding.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $6,518,000 $0 $6,518,000
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $24,482,000 $6,518,000 $0 $31,000,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$29,733,055
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The design development is advancing to 90%. Coordination with a Norfolk Southern project is ongoing. Work is progressing on Right-of-Way assessment and property acquisition assessment. There was also an executed change order to add a pedestrian tunnel for the project. Finally, the Forest Hill Flyover construction work continued during this reporting period.

Last Updated 06.10.2025

+ CREATE Ogden Junction (WA1) Track & Structure Rail $0 $0

Project Details

Description
The Ogden Junction (WA1) project will invest $170 million to improve a 1.9-mile-long segment of the Union Pacific rail line along Rockwell Avenue between Fulton Street on the north and 16th Street on the south. Improvements include the replacement of 14 (of 18) viaducts, rehabilitation of two viaducts, and permanent removal of two viaducts. All viaducts and bridges will be upgraded to modern design standards. Rail infrastructure improvements include the addition of a new, state-of-the-art bi-directional computerized traffic control system (TCS), upgraded rail switches (from manual to automatic), additional control points at Taylor Street, Ogden Avenue, and 16th Street, the crosstie replacement, “surfacing” to improve track foundation and alignment, and additional tracks to support fluidity and capacity. This funding represents Metra’s contribution to the project, other project partners within CREATE will contribute additional funding.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $500,000 $0 $0 $500,000

Last Updated 12.14.2023

+ Elmwood Park Grade Separation Track & Structure Rail $0 $10,000,000

Project Details

Description
Metra staff and the Village of Elmwood Park have coordinated on the Village’s proposal to construct a roadway flyover to eliminate a highway-rail grade crossing with Metra and freight trains. The Village engineers provided design alternatives that best fit Metra’s long-term needs and ensured the project would span the entire Metra right of way. Metra has committed to providing up to a $10 million contribution towards the proposed construction of the roadway flyover in return for preserving space for a future 4th and possible 5th main line track.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $10,000,000 $10,000,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $10,000,000 $10,000,000

Last Updated 12.19.2024

+ Hanover Park Crossings Track & Structure Rail $0 $0

Project Details

Description
Improvements to pedestrian crossings adjacent to the Hanover Park station along the MD-W.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $1,050,000 $0 $0 $1,050,000

Last Updated 12.16.2022

+ Rail Renewal BNS Track & Structure Rail $2,100,000 $6,955,000

Project Details

Description
Rail conditions are integral to maintaining safe operations and maintaining track speeds and on-time performance. These projects fund the refurbishment or replacement of rail and switches in the BNSF. Project activities may include but are not limited to, the renewal of switch points at various locations, the replacement of switch machines, AC heaters, the replacement of turnouts, and correcting minor defects with field welding. The high density of freight and commuter traffic, including extensive express service, requires close monitoring and periodic replacement of switches, switch machines, and sections of rail.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $2,100,000 $4,855,000 $6,955,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $5,240,000 $2,100,000 $4,855,000 $12,195,000

Last Updated 12.19.2024

+ Rail Renewal MED Track & Structure Rail $2,560,000 $10,580,000

Project Details

Description
Rail conditions are integral to maintaining safe operations and maintaining track speeds and on-time performance. These projects fund the refurbishment or replacement of rail and switches on the Metra Electric District. Project activities may include but are not limited to, the renewal of switch points at various locations, the replacement of switch machines, AC heaters, the replacement of turnouts, and correcting minor defects with field welding. The high density of freight and commuter traffic, including extensive express service, requires close monitoring and periodic replacement of switches, switch machines, and sections of rail.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $2,560,000 $8,020,000 $10,580,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $7,130,000 $2,560,000 $8,020,000 $17,710,000

Last Updated 12.19.2024

+ Rail Renewal MWD Track & Structure Rail $2,670,000 $14,380,000

Project Details

Description
Rail conditions are integral to maintaining safe operations and maintaining track speeds and on-time performance. These projects fund the refurbishment or replacement of rail and switches on the Milwaukee District. Project activities may include but are not limited to, the renewal of switch points at various locations, the replacement of switch machines, AC heaters, the replacement of turnouts, and correcting minor defects with field welding. The high density of freight and commuter traffic, including extensive express service, requires close monitoring and periodic replacement of switches, switch machines, and sections of rail.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $2,670,000 $11,710,000 $14,380,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $9,200,000 $2,670,000 $11,710,000 $23,580,000

Last Updated 12.19.2024

+ Rail Renewal RID Track & Structure Rail $1,900,000 $8,455,000

Project Details

Description
Rail conditions are integral to maintaining safe operations and maintaining track speeds and on-time performance. These projects fund the refurbishment or replacement of rail and switches on the Rock Island District. Project activities may include but are not limited to, the renewal of switch points at various locations, the replacement of switch machines, AC heaters, the replacement of turnouts, and correcting minor defects with field welding. The high density of freight and commuter traffic, including extensive express service, requires close monitoring and periodic replacement of switches, switch machines, and sections of rail.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $1,900,000 $6,555,000 $8,455,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $10,430,000 $1,900,000 $6,555,000 $18,885,000

Last Updated 12.19.2024

+ Rail Renewal UPR Track & Structure Rail $1,350,000 $4,850,000

Project Details

Description
Rail conditions are integral to maintaining safe operations and maintaining track speeds and on-time performance. These projects fund the refurbishment or replacement of rail and switches on the Union Pacific Railroad. Project activities may include but are not limited to, the renewal of switch points at various locations, the replacement of switch machines, AC heaters, the replacement of turnouts, and correcting minor defects with field welding. The high density of freight and commuter traffic, including extensive express service, requires close monitoring and periodic replacement of switches, switch machines, and sections of rail.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $1,350,000 $3,500,000 $4,850,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $3,250,000 $1,350,000 $3,500,000 $8,100,000

Last Updated 12.19.2024

+ Ties & Ballast MED Track & Structure Rail $0 $0 ✔︎

Project Details

Description
These projects consist of the replacement of cross ties, switch ties and ballast. In order to maintain proper track gauge and surface, it is necessary to replace ties and ballast periodically. This improves the riding quality of the trains and reduces the incidence of slow orders, which adversely affect adherence to train schedules. These projects represent part of an ongoing program to replace ties and ballast throughout the commuter territory.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $13,446,000 $0 $0 $13,446,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$4,100,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Major elements for this project included ironworkers; track, signal and utilities work. Track and structure improvements were completed during this reporting period and final invoices remain. This will be the final update on this project.

Last Updated 04.01.2024

+ Ties & Ballast MET Track & Structure Rail $14,652,500 $59,872,794 ✔︎

Project Details

Description
These projects fund capital renewal activities related to maintaining safe conditions along the right of way, including but not limited to the replacement of track ties, the cleaning or replacement of ballast, and the replacement of switch components and heaters. Periodically replacing ties and ballast is necessary to maintain proper track gauge and surface conditions. These projects fund improvements on Metra’s BNSF Line, the Metra Electric District, Milwaukee District, and Rock Island District and related rail yard facilities.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $7,000,000 $7,000,000
State $0 $14,652,500 $38,220,294 $52,872,794
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $10,780,000 $14,652,500 $45,220,294 $70,652,794

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$10,780,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Major elements for this project includes ironworkers; track, signal and utilities work. All work related to track and structure improvements were completed during this reporting period and final invoices remain. This will be the final update on this project.

Last Updated 09.12.2025

+ Ties & Ballast MWD-N Track & Structure Rail $0 $0

Project Details

Description
These projects consist of the replacement of cross ties, switch ties and ballast. In order to maintain proper track gauge and surface, it is necessary to replace ties and ballast periodically. This improves the riding quality of the trains and reduces the incidence of slow orders, which adversely affect adherence to train schedules. These projects represent part of an ongoing program to replace ties and ballast throughout the commuter territory. Projects on the Milwaukee District are split with the Canadian Pacific Railroad.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $5,170,000 $0 $0 $5,170,000

Last Updated 12.16.2022

+ Ties & Ballast MWD-W Track & Structure Rail $0 $0 ✔︎

Project Details

Description
Metra’s track renewal crew will rehabilitate dozens of miles of track along the Milwaukee District West (MD-W) Line in 2022. The project will be the most comprehensive investment in track conditions since Metra acquired the MD-W in 1987. Metra forces will Replace ties, clean or replace ballast, and replace switch components to provide smoother, faster, and safer track conditions. Metra partners with the Canadian Pacific Railroad to fund improvements to particular portions of the MD-W as freight train traffic degrade track conditions more rapidly than Metra trains.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $18,487,855 $0 $0 $18,487,855

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$4,331,634
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Track and structure improvements were completed during this reporting period. Major elements include ironworkers; track, signal and utilities work. This will be the final update on this project.

Last Updated 06.10.2024

+ Ties & Ballast RID Track & Structure Rail $0 $0 ✔︎

Project Details

Description
These projects consist of the replacement of cross ties, switch ties and ballast. In order to maintain proper track gauge and surface, it is necessary to replace ties and ballast periodically. This improves the riding quality of the trains and reduces the incidence of slow orders, which adversely affect adherence to train schedules. These projects represent part of an ongoing program to replace ties and ballast throughout the Rock Island District.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $7,520,000 $0 $0 $7,520,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$1,920,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Major elements for this project includes ironworkers; track, signal and utilities work. Track and structure improvements completed during this reporting period. This will be the final update on this project.

Last Updated 06.10.2024

+ Ties & Ballast UPR Track & Structure Rail $200,000 $1,200,000 ✔︎

Project Details

Description
Metra’s Union Pacific North (UP-N) Line will undergo significant rehabilitation in 2022. Union Pacific Railroad’s crews will replace ties, clean or replace ballast, and replace switch components on the northern extents of the UP-N Line. This project improves the riding quality of the trains and reduces the incidence of slow orders, which can impact the ability to maintain on-time performance. Metra provides funds to improve the track along the UP-N Line and other lines and yard facilities owned by the Union Pacific Railroad.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $200,000 $1,000,000 $1,200,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $4,500,000 $200,000 $1,000,000 $5,700,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$30,178,736
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Metra coordinated efforts with UP Forces for work on the Kenosha Sub tracks 1 & 2 related to replacing and cleaning ties, replacement of ballast, as well as switch components from Mile Post (MP) 8.5 to MP 52.1. This work was complete during this reporting period. Work continues and additional locations were added to the project. Kenosha ties work to follow Harvard MP .75 to MP 62 and are expected to begin in late Spring 2025.

Last Updated 06.10.2025

+ Ties, Ballast & Switch Heaters BNS Track & Structure Rail $3,975,000 $15,575,000

Project Details

Description
This project funds the replacement of ties, the cleaning or replacement of ballast, and the replacement of switch components and heaters. Periodically replacing ties and ballast is necessary to maintain proper track gauge and surface conditions. This project improves the riding quality of the trains and reduces the incidence of slow orders, which can impact the ability to maintain on-time performance. Metra provides funds to the BNSF Railroad to improve the track along the BNSF Line and rail yard facilities.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $3,975,000 $11,600,000 $15,575,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $10,200,000 $3,975,000 $11,600,000 $25,775,000

Last Updated 12.19.2024

+ Undercutting & Surfacing MDW Track & Structure Rail $0 $0

Project Details

Description
Track undercutting provides for the removal of all fouled track ballast, which is then cleaned and returned to the track bed. When the ballast is fouled, the load spreading capability is lost. Undercutting is necessary when the ballast section has become so contaminated that normal ballasting and surfacing will no longer hold a proper track surface. The results of undercutting are a smooth, well-aligned track surface, extended tie and ballast life and reduced ongoing maintenance expense. This work will be done on the Milwaukee District West.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $3,250,000 $0 $0 $3,250,000

Last Updated 12.16.2022

+ Undercutting & Surfacing MED Track & Structure Rail $0 $0

Project Details

Description
Track undercutting provides for the removal of all fouled track ballast, which is then cleaned and returned to the track bed. When the ballast is fouled, the load spreading capability is lost. Undercutting is necessary when the ballast section has become so contaminated that normal ballasting and surfacing will no longer hold a proper track surface. The results of undercutting are a smooth, well-aligned track surface, extended tie and ballast life and reduced ongoing maintenance expense. This work will be done systemwide
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $4,050,000 $0 $0 $4,050,000

Last Updated 12.16.2022

+ Undercutting & Surfacing MET Track & Structure Rail $2,900,000 $12,760,000

Project Details

Description
Track undercutting provides for the removal of all fouled track ballast, which is then cleaned and returned to the trackbed. When the ballast is fouled, the load-spreading capability is lost. Undercutting is necessary when the ballast section has become so contaminated that normal ballasting and surfacing will no longer hold a proper track surface. The results of undercutting are a smooth, well-aligned track surface, extended tie, and ballast life, and reduced ongoing maintenance expense. This work will be done on the Metra Electric District.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $2,900,000 $9,860,000 $12,760,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $3,440,000 $2,900,000 $9,860,000 $16,200,000

Last Updated 12.19.2024

+ Undercutting & Surfacing RID Track & Structure Rail $0 $0

Project Details

Description
Track undercutting provides for the removal of all fouled track ballast, which is then cleaned and returned to the track bed. When the ballast is fouled, the load spreading capability is lost. Undercutting is necessary when the ballast section has become so contaminated that normal ballasting and surfacing will no longer hold a proper track surface. The results of undercutting are a smooth, well-aligned track surface, extended tie and ballast life and reduced ongoing maintenance expense. This work will be done on the Rock Island District.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $4,630,000 $0 $0 $4,630,000

Last Updated 03.16.2023

+ Undercutting & Surfacing UPR Track & Structure Rail $0 $0

Project Details

Description
Track undercutting provides for the removal of all fouled track ballast, which is then cleaned and returned to the track bed. When the ballast is fouled, the load spreading capability is lost. Undercutting is necessary when the ballast section has become so contaminated that normal ballasting and surfacing will no longer hold a proper track surface. The results of undercutting are a smooth, well-aligned track surface, extended tie and ballast life and reduced ongoing maintenance expense. This work will be done on the Union Pacific Lines.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $1,250,000 $0 $0 $1,250,000

Last Updated 12.16.2022

+ Union Pacific West Line Expansion Track & Structure Rail $0 $0 ✔︎

Project Details

Description
This project, a Public-Private Partnership between Metra and the Union Pacific Railroad, will construct two new segments of third mainline track on the Union Pacific West Line. One of the segments will be between the Vale Interlocking at milepost 10.0 in River Forest and the 25th Avenue Interlocking at milepost 11.8 in Melrose Park. The other segment will be between the Kress Interlocking at milepost 32.1 in West Chicago and the Peck Interlocking at milepost 38.4 in Geneva. Improvements are anticipated for all four of the interlockers that bookend the two segments. Additionally, a new interlocker may be constructed at milepost 35.4 between the Kress and Peck interlockers, which will increase operational flexibility. The interlocker improvements and additions will be constructed to meet Positive Train Control requirements. Improvements along both segments will include, but not be limited to, trackwork, earthwork, sub-ballast, structures, signal infrastructure, interlocking upgrades, and all work necessary at highway grade crossings. Bridge improvements will be needed over both the Des Plaines River and the Fox River to allow for the third mainline track. The project will also include platform relocations and improvements at both the Maywood and Melrose Park stations, and platform, platform shelter, and parking improvements at the Geneva station. Lastly, land acquisition may be required at various locations along the two segments in areas where the right of way is not wide enough to accommodate the third main track within the track centers required by the Union Pacific.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $50,000 $0 $0 $50,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$127,477,280
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
This project has reached substantial completion. The RTA PMO team performed a final walk through in May 2025. This will be the last report on this project.

Last Updated 06.10.2025

+ Metra Bridge Replacement and Repair Rail $39,745,000 $290,475,000 $2,032,450,613 $1,741,975,613

Replace and repair over 100 bridges systemwide.

Toggle Project Title Asset Category Mode 2025 Funding 2025-2029 Funding PMO
+ 96th Ave. Bridge Track & Structure Rail $6,655,000 $6,655,000 ✔︎

Project Details

Description
This project funds the replacement of Bridge 275 on Metra’s Rock Island District. The 94-year-old bridge spans over 96th Avenue in Mokena at milepost 27.5.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $6,655,000 $0 $6,655,000
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $2,800,000 $6,655,000 $0 $9,455,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$2,800,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
This project is in the final design development phase. The 90% design has been completed, and it is advancing to 100% completion. The permitting process for construction has been started with the Village of Mokena.

Last Updated 06.10.2025

+ Bridge 86 - 78th St Entrance Track & Structure Rail $7,200,000 $32,635,000 ✔︎

Project Details

Description
Engineering Design, construction, and related services for the replacement of Bridge 86 on the Rock Island (RI) Line will be funded by this project. Bridge 86 dates back to 1916 and spans 78th Street at milepost 8.62 in the Auburn Gresham neighborhood of Chicago. Contemporary construction methods will allow two-track service to be maintained during the bridge replacement. The replacement abutment wall at the south end of the bridge will include ground-floor space for a leasable storefront, a new staircase, and an elevator. The elevator and stairs will provide an accessible pathway from 79th Street to the new Auburn Park station boarding platforms and headhouse. This project is a necessary component of the new Auburn Park station project.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $7,200,000 $25,435,000 $32,635,000
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $5,631,000 $7,200,000 $25,435,000 $38,266,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$14,980,365
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The designer for the bridge and entrance submitted the 100% design and was reviewed by Metra. Constructability review was completed and revised drawings are still in progress and under review to begin the procurement for construction. The procurement process for the construction manager has been initiated.

Last Updated 09.12.2025

+ Bridge A-32 Reconstruction Track & Structure Rail $0 $0 ✔︎

Project Details

Description
The bridge that carries the Milwaukee District North Line over Milwaukee Avenue near Kilbourne Avenue was built in 1899. It will be replaced with a new bridge with new abutments. Grayland Station, just south of the bridge, will be rebuilt with longer platforms, new public address equipment, visual information signs, shelters with on-demand heat on each side, new lighting and new stairs and ramps, making it fully ADA-compliant.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$39,359,109
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The construction contract was awarded in October 2020 and the construction management contract was awarded in February 2021. The contractor continues to make headway with construction activities during this reporting period. The bridge steel girders were delivered and installed, and waterproofing of the bridge deck were completed. Bridge work has been completed and station site construction has begun with platform construction in progress. The project is 91% complete.

Last Updated 06.10.2025

+ Bridge A110/56 Track & Structure Rail $0 $0

Project Details

Description
This project funds the replacement of Bridges A110 and A56 on Metra’s Milwaukee District North (MD-N) Line. Both bridges were constructed in 1909 and span the North Branch Chicago River. Bridge A110 is located in Northbrook at milepost 21.3 and Bridge A56 is at milepost 10.85 in Chicago just south of the Edgebrook station. This is a multi-year, multi-phase project that will fund design engineering services and any environmental analyses as required by the National Environmental Policy Act (NEPA). Construction funds are provided in later years.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $3,145,000 $0 $0 $3,145,000

Last Updated 12.19.2024

+ Bridge A318 Track & Structure Rail $0 $0

Project Details

Description
This project funds design services and the construction of a replacement bridge that will increase the capacity of trains and service on the Milwaukee District North (MD-N) Line. The new Bridge A318 will add a second-track siding over the North Branch Chicago River in Rondout at milepost 32.4. A second-track siding will allow for additional train movements through the Fox Lake Subdivision, which runs northwest of Rondout and includes seven stations. This is a multi-year project that works in concert with the separate projects to improve the Rondout Interlocking, the Rondout CP Tri-State track, and the Lake Forest Crossovers.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $4,647,000 $0 $0 $4,647,000

Last Updated 12.19.2024

+ Bridge A418 Track & Structure Rail $0 $0

Project Details

Description
This project funds the engineering design of a bridge replacement that spans the Mud Creek in Long Lake at milepost 45.8. The project has construction funds in following year to replace the circa 1909 structure on the Fox Lake Subdivision, which runs north-west from Rondout to Fox Lake along the Milwaukee District North Line.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $10,300,000 $0 $0 $10,300,000

Last Updated 03.16.2023

+ Bridge Improvement Program Track & Structure Rail $0 $120,000,000

Project Details

Description
Metra trains traverse 926 railroad bridges across the system. Metra owns 446 railroad bridges including 233 that are over 100 years old. While every bridge is in safe working condition and inspected by qualified engineers at least one each year, these aging bridges are past due for life-extending rehabilitation or full replacement. This project is intended to address deteriorating bridge conditions by rehabilitating 5 bridges per year and replacing 5 bridges per year.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $120,000,000 $120,000,000
Total $0 $0 $120,000,000 $120,000,000

Last Updated 12.19.2024

+ Bridge Rehabilitation Program Track & Structure Rail $3,310,000 $6,925,000

Project Details

Description
This on-going project will fund the preliminary engineering phase and environmental analyses as required by the National Environmental Policy Act (NEPA) for up to five proposed bridge rehabilitation projects per year. Projects that advance to the final design and construction phases will be funded by new, location-specific project numbers as funding becomes available. Specific bridge rehabilitation project locations are to be determined based on reviewing annual bridge condition inspections, bridge sufficiency ratings, and other factors that will inform which bridges can be improved with a life-extending rehabilitation. The bridge rehabilitation program is a multi-year project. Final design and construction funds have not been identified for 2024 activities that will be funded by this project
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $3,310,000 $3,615,000 $6,925,000
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $3,215,000 $3,310,000 $3,615,000 $10,140,000

Last Updated 12.19.2024

+ Bridge Replacement Program Track & Structure Rail $6,600,000 $14,100,000

Project Details

Description
This on-going project will fund the preliminary engineering phase and environmental analyses as required by the National Environmental Policy Act (NEPA) for up to five proposed bridge replacement projects per year. Projects that advance to the final design and construction phases will be funded by new, location-specific project numbers as funding becomes available. Specific bridge replacement project locations are to be determined based on priority needs, annual bridge condition inspections, bridge sufficiency ratings, and the potential for bundling multiple bridge replacement projects in one construction contract procurement. The bridge replacement program is a multi-year project. Final design and construction funds have not been identified for 2024 activities that will be funded by this project.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $6,600,000 $7,500,000 $14,100,000
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $6,660,000 $6,600,000 $7,500,000 $20,760,000

Last Updated 12.19.2024

+ Bridges & Retaining Walls BNS Track & Structure Rail $3,500,000 $12,700,000

Project Details

Description
This project will provide for the rehabilitation of retaining walls on the BNSF commuter line. Retaining wall sections at intermittent locations along the right-of-way will be rehabilitated. This work typically includes complete reconstruction with steel sheet piling, concrete panels or bin wall to prevent retaining wall deterioration that can result in destabilization of the roadbed and in turn lead to track shifting.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $3,500,000 $9,200,000 $12,700,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $9,300,000 $3,500,000 $9,200,000 $22,000,000

Last Updated 12.19.2024

+ Bridges & Retaining Walls MED Track & Structure Rail $2,200,000 $10,000,000

Project Details

Description
These projects improvement of bridges and the rehabilitation of retaining walls at various locations in the Metra Electric District to prevent structural issues. Project funds proactively address deterioration that can result in the destabilization of the roadbed, track shifting, and slow orders. Bridge improvements may include but are not limited to the rehabilitation of wing walls, addressing cracked bearing blocks, renewing bridge seats on abutments, and protective coating. Project funds may be used for engineering design services, installation of outer-track fencing, the addition of concrete panels or bin walls, or reconstruction of retaining wall sections with steel sheet piling as needed. Specific improvements will be determined based on a survey of field conditions.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $2,200,000 $7,800,000 $10,000,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $6,140,000 $2,200,000 $7,800,000 $16,140,000

Last Updated 12.19.2024

+ Bridges & Retaining Walls MWD Track & Structure Rail $1,350,000 $6,200,000

Project Details

Description
These projects improvement of bridges and the rehabilitation of retaining walls at various locations on the Milwaukee District West to prevent structural issues. Project funds proactively address deterioration that can result in the destabilization of the roadbed, track shifting, and slow orders. Bridge improvements may include but are not limited to the rehabilitation of wing walls, addressing cracked bearing blocks, renewing bridge seats on abutments, and protective coating. Project funds may be used for engineering design services, installation of outer-track fencing, the addition of concrete panels or bin walls, or reconstruction of retaining wall sections with steel sheet piling as needed. Specific improvements will be determined based on a survey of field conditions.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $1,350,000 $4,850,000 $6,200,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $1,450,000 $1,350,000 $4,850,000 $7,650,000

Last Updated 12.19.2024

+ Bridges & Retaining Walls RID Track & Structure Rail $1,980,000 $8,530,000

Project Details

Description
These projects improvement of bridges and the rehabilitation of retaining walls at various locations on the Rock island District to prevent structural issues. Project funds proactively address deterioration that can result in the destabilization of the roadbed, track shifting, and slow orders. Bridge improvements may include but are not limited to the rehabilitation of wing walls, addressing cracked bearing blocks, renewing bridge seats on abutments, and protective coating. Project funds may be used for engineering design services, installation of outer-track fencing, the addition of concrete panels or bin walls, or reconstruction of retaining wall sections with steel sheet piling as needed. Specific improvements will be determined based on a survey of field conditions.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $1,980,000 $6,550,000 $8,530,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $13,500,000 $1,980,000 $6,550,000 $22,030,000

Last Updated 12.19.2024

+ Bridges & Retaining Walls UPR Track & Structure Rail $1,350,000 $9,350,000

Project Details

Description
These projects improvement of bridges and the rehabilitation of retaining walls at various locations on the Union Pacific Railroad to prevent structural issues. Project funds proactively address deterioration that can result in the destabilization of the roadbed, track shifting, and slow orders. Bridge improvements may include but are not limited to the rehabilitation of wing walls, addressing cracked bearing blocks, renewing bridge seats on abutments, and protective coating. Project funds may be used for engineering design services, installation of outer-track fencing, the addition of concrete panels or bin walls, or reconstruction of retaining wall sections with steel sheet piling as needed. Specific improvements will be determined based on a survey of field conditions.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $1,350,000 $8,000,000 $9,350,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $4,200,000 $1,350,000 $8,000,000 $13,550,000

Last Updated 12.19.2024

+ CREATE EW-2 Bridge Lift Track & Structure Rail $4,600,000 $4,600,000 ✔︎

Project Details

Description
This project involves lifting a bridge between 78th Street and 79th Street on Metra’s Rock Island Line. The bridge spans over three sets of railroad tracks owned by The Belt Railway of Chicago and Norfolk Southern in Chicago at milepost 8.7. This project is a necessary component of the new Auburn Park station project.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $4,600,000 $0 $4,600,000
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $14,980,366 $4,600,000 $0 $19,580,366

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$11,271,349
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The design for the project has been completed. Metra advertised the construction procurement and received only one bid. The proposed cost exceeded the allocated construction budget for the project. Metra decided to re-design the project to reduce the risk of the potential contractor and attract more bids. A change order was issued to the designer. The re-design was completed, and a new procurement package has been developed and advertised and still waiting for bids to be received.

Last Updated 09.12.2025

+ Evanston Bridge Repainting Track & Structure Rail $0 $0 ✔︎

Project Details

Description
This project involves the sanding, abatement and repainting of the Dempster Street and Davis Streetbridges in Evanston on the Union Pacific North Line.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $1,200,000 $0 $0 $1,200,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$3,300,000
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The contractor finished painting and applying the protective coating on the bridge in December. Final invoices remain and this will be the final update on this project.

Last Updated 03.27.2025

+ Grand Avenue Bridge Track & Structure Rail $0 $0

Project Details

Description
This project funds engineering design services for the replacement of the Grand Avenue Bridge. Three main line tracks utilize the bridge including the Milwaukee District North and West Lines and the North Central Service. The bridge, constructed in 1898, spans over the intersection of Grand Avenue and Homan Avenue at milepost 4.5. Construction funds are provided in future years.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $16,000,000 $0 $0 $16,000,000

Last Updated 12.16.2022

+ Gresham Area Bridges Track & Structure Rail $0 $0 ✔︎

Project Details

Description
This project funds the remainder of construction costs to replace two bridges on the Rock Island (RI) Line in the Auburn Gresham neighborhood of Chicago. The Vincennes Bridge on the RI Main Line is a concrete structure built in 1916 at milepost 9.75. The Morgan Bridge on the RI Beverly Branch is a timber structure at milepost 10.15 and was erected in 1973 by the now-defunct Rock Island Railroad with the intention of being a temporary solution. Both bridges are named after the Chicago street over which they cross, carry two main line tracks, and will be replaced with resilient concrete bridges.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $12,000,000 $0 $0 $12,000,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$27,324,873
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Construction activities are ongoing. The contractor completed all work on the remediation plan related to construction of the caisson’s. The northwest and northeast grade beams were formed and poured in addition to east and west pier closure walls. The contractor is working on assembling the bridge steel structure and replacing the bridge.

Last Updated 09.12.2025

+ Hickory Creek Bridge Track & Structure Rail $0 $0 ✔︎

Project Details

Description
This project funds repair activities to rehabilitate the existing piers and abutments. The existing bridge spans the Hickory Creek.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $273,100,000 $0 $0 $273,100,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$2,750,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The project is in the design phase. NEPA activities continue and the 100% design was submitted and under Metra review. Permitting activities continue.

Last Updated 09.12.2025

+ Stoney Creek Bridge- SWS Track & Structure Rail $0 $0 ✔︎

Project Details

Description
This project funds engineering design services for the replacement of the Stoney Creek Bridge on Metra’s SouthWest Service. The bridge, constructed in 1917, spans over Stoney Creek in Oak Lawn at milepost 16.3. Construction funds are provided in future years.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $18,230,000 $0 $0 $18,230,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$18,230,000
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The 95% design has been submitted to Metra and it was reviewed. The designer is working towards the 100% design and the design permitting activities continued.

Last Updated 09.12.2025

+ UP North Line - North 11 Bridges and Ravenswood Station Track & Structure Rail $0 $0 ✔︎

Project Details

Description
This project involves the replacement of 22 bridges on the UP North Line in Chicago, Illinois. The structural scope of work will include, but not be limited to, replacement of existing stone abutments, retaining wall construction, steel spans, and decks. Also, some track work will be accomplished between the bridges, including the replacement of wood ties with concrete ties, and some commuter station modifications will be required, including the Ravenswood Station. To ensure reliable train operations, theproject will include various signal improvements, including: new interlockers at Addison Street (MP 5.0) and Rosehill (MP 7.3, between Balmoral Avenue and Bryn Mawr Avenue), and upgrades to the Deering interlocker (MP 3.2). In
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $983,006 $0 $0 $983,006

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$50,255,463
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The bridge construction has been completed in September 2021. The station contractor reached substantial completion in August 2023. The contractor continues to address punch list items on the station. The station had a soft opening at the beginning of August and its opening ceremony at the beginning of October. This will be the final update of this project.

Last Updated 12.14.2023

+ UP North Line - South 11 Bridges Track & Structure Rail $1,000,000 $58,780,000 ✔︎

Project Details

Description
The project will remove the 11 existing Union Pacific North (UP-N) Line bridges over local roads and streets in the City of Chicago. The 11 bridges will be replaced with single-span bridges designed with three through plate girders and new abutments. Each bridge will also require a walkway and sacrificial girders along the outer girders. Nearly 2 miles of retaining walls will be replaced and several miles of track, ties, and ballast will be installed. The construction will be staged and phased to ensure that two tracks will remain in service throughout the duration of construction to limit service disruptions.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $1,000,000 $57,780,000 $58,780,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $7,690,000 $1,000,000 $57,780,000 $66,470,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$279,100,000
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
This project is in the final design phase. It has been separated into 3 segments. The design for the first segment has been completed. Currently Metra is working with the designer on a construction procurement package and the Issue for Bid documents to be advertised for bid later this year. The advance work on tree removal is in progress. Community outreach activities continue.

Last Updated 09.12.2025

+ Z14C- Keystone Ave. Bridge Track & Structure Rail $0 $0

Project Details

Description
This project funds engineering design services for the replacement of the Z 14 C in Chicago. The bridge, constructed in 1903, spans over the intersection of Keystone Avenue Bridge at milepost 5.69. Construction funds are provided in future years.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $6,709,758 $0 $0 $6,709,758

Last Updated 12.19.2024

+ CTA Mid-Life Bus Overhauls Bus $36,689,623 $98,807,627 $326,807,627 $228,000,000

Overhauls to maintain vehicles, ensure reliability and enable to perform through full useful life.

Toggle Project Title Asset Category Mode 2025 Funding 2025-2029 Funding PMO
+ Bus Overhaul - Mid-Life 450 Nova (7900 Series) Rolling Stock Bus $36,689,623 $98,807,627

Project Details

Description
Funding will provide for the mid-life overhaul of the CTA Nova buses 7900 Series. Buses placed into service between 2014 and 2017 will receive a bus overhaul and will be returned to a state of good repair. This scheduled Mid-Life Bus Overhaul Program will allow for safe, effective operation of the buses throughout their standard estimated life of 15 years.Major components, which are a part of the overhaul, include items such as engines, transmissions, electronics (including cameras, GPS, destination signs, voice announcements, and passenger counters), HAVC, cooling and suspension systems, doors, wheel chair ramps, driver seats, interior lighting, and other components as needed.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $36,689,623 $49,478,674 $86,168,297
State $0 $0 $12,639,330 $12,639,330
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $15,150,000 $36,689,623 $62,118,004 $113,957,627

Last Updated 12.19.2024

+ Pace Fixed Route Buses - Electric Bus $36,000,018 $173,949,056 $629,200,000 $455,250,944

Replacement of buses reaching useful life with electric buses.

Toggle Project Title Asset Category Mode 2025 Funding 2025-2029 Funding PMO
+ Fixed Route Electric Buses Rolling Stock Bus $36,000,018 $173,949,056 ✔︎

Project Details

Description
Replacement battery-electric buses including associated equipment (cameras, destination signs, etc.) and services (Buy America audit and inspections) for fixed route services operating systemwide.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $135,655,414 $135,655,414
State $0 $27,000,000 $0 $27,000,000
RTA $0 $0 $2,293,624 $2,293,624
Service Board / Local $0 $9,000,018 $0 $9,000,018
Total $2,050,000 $36,000,018 $137,949,038 $175,999,056

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$28,749,859
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The contract was executed, and the vendor originally provided Pace with an updated production schedule due to previous supply chain issues and long lead time items. However, the vendor was bought out by a new company, Phoenix Cars, LLC. Since the change, Phoenix has provided Pace with an updated delivery schedule. Production of the buses will start by July 2025 and delivery to begin in Q4-2025 and last vehicle is expected to be delivered in Q1-2026.

Last Updated 06.10.2025

+ Pace Improve Support Facilities Bus $31,500,000 $91,500,000 $607,522,125 $516,022,125

Includes North, Southwest, River, North Shore, and Wheeling Divisions - Electrification/Expansion.

Toggle Project Title Asset Category Mode 2025 Funding 2025-2029 Funding PMO
+ Construct Salt Shed Support Facilities & Equipment Bus $0 $0 ✔︎

Project Details

Description
Pace is in need of a stand-alone storage solution and will construct a shed to store and secure up to 10tons of bulk rock salt that is used during the winter season. The construction of the shed will be within thefootprint of Pace's parcel. This shed will allow for accessible use with Pace's skidsteer to load rock saltonto the pickup trucks and distribute it on approximately more than 15,000 square yards of grounds(parking lots and driveways), in addition to sidewalks, in a safe and more efficient manner. CurrentlyPace purchases 50-pound bags of salt that have to be loaded manually which has become very unsafein term of personal injury risk and is very time consuming as it has to be loaded multiple times per day.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $14,750,000 $0 $0 $14,750,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$75,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
A construction contract was awarded. There were some delays related to the Village code requirements and permits. All activities were completed during this reporting period and final invoices remain. This will be the final update on this project.

Last Updated 06.22.2023

+ Fire Loop System Support Facilities & Equipment Bus $0 $0

Project Details

Description
Replacement of underground loop, piping, valves, and pump for fire suppression.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $3,250,000 $0 $0 $3,250,000

Last Updated 12.16.2022

+ Headquarters Renovation Support Facilities & Equipment Bus $0 $0

Project Details

Description
Paint and carpet replacement at Administrative Office in Arlington Heights. HQ is currently 2 floors of employees with the building capable of a 3rd floor structure. Adding a third floor we would incorporate high efficient heating and cooling with hospital grade filters update the colors and carpet and workspace on the first and second floor to match the third floor.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $750,000 $0 $0 $750,000

Last Updated 12.16.2022

+ North Division Electrification/Expansion Support Facilities & Equipment Bus $0 $0 ✔︎

Project Details

Description
Renovation and expansion of North Division Garage located in Waukegan, including installation of charging capabilities for electric buses.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $130,870,359 $0 $0 $130,870,359

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$12,543,862
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Pace has issued a Notice to Proceed for a progressive design build contract in June 2024. The design has been completed and construction activities continued with underground work is ongoing. The contractor continued working on the subbase and duct work as well. Charging equipment was delivered and installed. Construction activities continue.

Last Updated 09.12.2025

+ Southwest Division Electrification/Expansion Support Facilities & Equipment Bus $31,500,000 $91,500,000

Project Details

Description
Renovation of Southwest Division Garage located in Bridgeview, adding indoor bus capacity from 40 to 70, including office space and installation of charging capabilities for electric buses.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $31,500,000 $60,000,000 $91,500,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $3,628,767 $31,500,000 $60,000,000 $95,128,767

Last Updated 12.19.2024

+ CTA Replacement Bus Purchase 1000 Series - 430 Electric Buses Bus $31,255,875 $31,255,875 $559,000,000 $527,744,125

Replace 430 of the 1000 Series Buses, with electric buses, that have now been in service 15 yrs plus and are now due replacement.

Toggle Project Title Asset Category Mode 2025 Funding 2025-2029 Funding PMO
+ Purchase Electric Buses Rolling Stock Bus $31,255,875 $31,255,875

Project Details

Description
CTA will purchase electric buses to replace 1000 series buses.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $31,255,875 $0 $31,255,875
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $31,255,875 $0 $31,255,875

Last Updated 09.11.2025

+ Purchase up to 6 Electric Buses with Charging Systems Rolling Stock Bus $0 $0

Project Details

Description
Bus funding provides for a future order of up to six 40-foot battery-powered, zero-emission, all-electric, fully accessible, public transit buses with en-route charging capabilities. CTA will retire up to six 1000-Series New Flyer buses that are over 14 years old. Turnkey project to procure Electric buses and associated charging infrastructure.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

Last Updated 12.14.2023

+ Purchase up to 70 Electric Buses and up to 9 Charging Stations Rolling Stock Bus $0 $0 ✔︎

Project Details

Description
Purchase up to 70 Electric Buses and up to nine Chargers - Bus funding provides for a future order of up to 70 40-foot battery-powered, zero-emission, all-electric, fully accessible, public transit buses with en-route charging capabilities. CTA will retire up to 70 1000-Series New Flyer buses that are over 14 years old. Turnkey project to procure Electric buses and associated charging infrastructure.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $23,541,688 $0 $0 $23,541,688

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$71,991,905
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The charging stations were received and installed and reached substantial completion in January 2021. In Q4-2021, seventeen (17) production buses were completed and delivered to CTA. The installation of revenue fare collection systems, communication equipment, network systems were completed in Q2-2022. A total of twenty-three (23) buses were delivered. Nineteen (19) are in service and four are being used at the 74th Garage for operator training. CTA previously exercised an option for an additional twenty-two (22) buses. CTA is working on the pre-build process of finalizing engineering configuration. Pre-production activities continued where production is expected to start in June 2025 and delivery of the first vehicle is expected by the end of 2025.

Last Updated 06.10.2025

+ CTA Railcar Overhauls Rail $30,241,135 $188,744,174 $481,003,968 $292,259,794

Quarter-life overhaul of 5000-series rail cars and life-extending overhauls of older 2600 and 3200-series rail cars.

Toggle Project Title Asset Category Mode 2025 Funding 2025-2029 Funding PMO
+ 5000 Series Rail Car Quarter Life Overhaul Rolling Stock Rail $1,899,057 $1,899,057 ✔︎

Project Details

Description
5000 Series Qtr. Overhaul - 714 Cars - The scope of this project is to provide for the Quarter?Life Overhaul on the 5000?Series rail cars. Schedule maintenance will include major component rebuilds and needed repairs to the car bodies. Additional work may include: replacing control groups, air conditioning units, truck assemblies, including traction motors, cables, batteries, brake calipers, axle assemblies, interior seat modification and other critical components based on condition assessment.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $1,899,057 $0 $1,899,057
Total $333,702,915 $1,899,057 $0 $335,601,972

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$400,000,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
As of the beginning of September, 612 out of 714 cars have completed the overhaul process. CTA continues to receive material kits and overhaul cars. CTA forces decreased the overhaul rate from 14 cars per month down to 8 rail cars per month for the remainder of this project to match previous overhaul rates.

Last Updated 09.12.2025

+ Life Extending Overhaul 2600 & 3200's Series - Propulsion Kits Rolling Stock Rail $18,292,078 $57,589,672

Project Details

Description
Project will replace the propulsion control system on all 3200 series rail cars and the option to replace the propulsion control system on another 200 of the 2600-series rail cars. The new propulsion control system with a solid-state technology will provide power to the rail cars in a more energy efficient and reliable way. This system will allow regeneration of power back to the third rail during braking, reducing overall energy usage.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $18,292,078 $33,970,943 $52,263,021
State $0 $0 $5,326,651 $5,326,651
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $18,292,078 $39,297,594 $57,589,672

Last Updated 12.19.2024

+ Life extending Overhaul 2600/3200 Series Rolling Stock Rail $0 $119,105,445

Project Details

Description
Life extending overhaul on the 258 3200 Series and 300 2600 Series cars. Work on these cars will focus on major systems starting with the proplusion/powering.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $94,698,795 $94,698,795
State $0 $0 $24,406,650 $24,406,650
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $119,105,445 $119,105,445

Last Updated 12.19.2024

+ Replace video system 3200 and 5000-Series railcars Rolling Stock Rail $10,050,000 $10,150,000 ✔︎

Project Details

Description
Replace the existing video system on the 5000-series rail cars which is obsolete and no longer supported by the vendor. Replace existing video system on the 3200-series rail cars with a more reliable system. Useable components removed from the 3200s will be re-used to support the same system on the 2600-seriese rail cars.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $10,050,000 $100,000 $10,150,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $6,500,000 $10,050,000 $100,000 $16,650,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$25,100,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
CTA finalized the procurement process and the contract was awarded to Railhead Corporation. The contractor completed the design and began delivery of pre-production video recorder kits. The installation of the system of the system in the first unit (2 cars) is ongoing. The installation of the remaining preproduction units will continue.

Last Updated 06.10.2025

+ CTA Systemwide Station Program System $29,659,157 $86,927,786 $115,178,681 $28,250,895

Station upgrades, modernization and accessibility improvements.

Toggle Project Title Asset Category Mode 2025 Funding 2025-2029 Funding PMO
+ 43rd Street Station Green Line - Improvements Stations & Passenger Facilities Rail $3,020,887 $3,020,887

Project Details

Description
Project will revise an exit only stair to reduce the street level footprint and make other aesthetic and state-of-good repair upgrades to coordinate with an upcoming new adjacent development.Creates a Green Line TOD project at 43rd Station in Southeast side of the City and provides for an enhanced environment to sustain the redevelopment occurring within the neighborhood.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $3,020,887 $0 $3,020,887
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $30,162,349 $3,020,887 $0 $33,183,236

Last Updated 09.11.2025

+ Central Station (Purple Line) - Stair Replacement Stations & Passenger Facilities Rail $0 $0

Project Details

Description
Replace Central Station stairway, in Evanston, which include risers, treads, stair stringers, handrails, guardrails, canopies and enclosures.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $7,024,058 $0 $0 $7,024,058

Last Updated 12.16.2022

+ Clark and Lake Stair Replacement Stations & Passenger Facilities Rail $0 $0

Project Details

Description
Replace stairs at mezzanine level at Blue Line Clark and Lake Station.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $177,485 $0 $0 $177,485

Last Updated 12.16.2022

+ Clark and Lake Thompson Center Development Stations & Passenger Facilities Rail $8,638,270 $8,638,270

Project Details

Description
The redevelopment of the former James R. Thompson Center (JRTC)1 represents a major opportunity for modernizing the adjacent Clark/Lake Station, one of Chicago’s busiest and most vital transit hubs. JRTC is located at 100 W Randolph Street in Chicago Loop.This project addresses the need to maintain uninterrupted operations while upgrading the station to meet future ridership demands and modern standards for capacity, accessibility, and safety.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $8,638,270 $0 $8,638,270
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $8,638,270 $0 $8,638,270

Last Updated 09.11.2025

+ Cottage Grove Station Stations & Passenger Facilities Rail $0 $0 ✔︎

Project Details

Description
CTA has partnered with the Preservation of Affordable Housing (POAH) to revitalize the southeastcorner of 63rd Street and Cottage Grove Avenue with a new multi-use office/retail space, which willcontain a new Cottage Grove station house. Overall the general design concept relocates the CottageGrove station house within POAH's new Woodlawn Crossing mixed-use development at the southeastcorner of 63rd Street and Cottage Grove Avenue, while the existing platforms and other related railinfrastructure will remain in their current locations. The POAH design concept also adds a newpedestrian bridge and canopy to connect the existing platforms to POAH's Woodlawn Crossing building.The project will dramatically decrease the footprint of the CTA's Cottage Grove station over theintersection of 63rd Street and Cottage Grove, which will provide more natural light at street-level anddirectly respond to community feedback. The project features a number of station enhancements thatwill improve customer experience, including attractive new sculptural canopies, contemporary stationfinishes, a new elevator, and brighter lighting inside the station and on the platform. This funding willprovide for the demolition of the existing station house and canopy, new stationhouse including finisheswithin a new multi-use office/retail space conforming to CTA standards and criteria, platform extensions,new stairs from platform to grade, a new platform canopy, new friction buffer stops and associated trackwork, structural steel girder and stringer repairs, new lighting, new signage, and new train operator'sfacility.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $61,034,470 $0 $0 $61,034,470

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$61,469,049
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
A design contract has been awarded in January 2021 and CTA has issued a Notice to Proceed. The 60% design has been completed. Negotiations with Preservation of Affordable Housing (POAH) and City of Chicago Department of Planning and Development (CDPD) on final design for building where station entrance will be located are ongoing. POAH procured their own designer to support this project. Design is currently on hold until an agreement is reached with POAH and CDPD. As track and workforce availability allows, CTA internal forces are working on the structural and track component of the project.

Last Updated 06.10.2025

+ Loyola Station Red Line - Stair and Elevator Replacement Stations & Passenger Facilities Rail $0 $0

Project Details

Description
Project will reconstruct or replace the existing cast-in-place concrete stairs that go from the main stationhouse to the elevated platform. Additionally, the traction elevator will be fully replaced with all new components including cab, platform, cables, motor, and controller.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $12,000,000 $0 $0 $12,000,000

Last Updated 12.16.2022

+ Park & Ride Improvements Stations & Passenger Facilities System $0 $0

Project Details

Description
Capital maintenance work is necessary to improve or maintain parking lots at a SOGR. Renewal work for priority locations includes concrete structure restoration, surface paving, curb and sidewalk, drainage systems, and installation of parking machines.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

Last Updated 12.16.2022

+ Public Address Communication Modernization & Upgrade Stations & Passenger Facilities Rail $6,000,000 $14,000,000

Project Details

Description
Project will provide for the comprehensive overhaul of CTA's Public Address System to upgrade the Authority's PA system from antiquated and obsolete technology to modern digital technology with disaster recovery/business continuity solutions, increased capacity, and compliance with NFPA 130. The PA system upgrade will include the upgrade/replacement of the master head-end system at the Control Center and Backup Control Center, and remote systems at each rail station, with ancillary physical infrastructure.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $6,000,000 $6,000,000 $12,000,000
State $0 $0 $2,000,000 $2,000,000
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $6,000,000 $8,000,000 $14,000,000

Last Updated 12.19.2024

+ Quincy Loop Station Upgrade Stations & Passenger Facilities Rail $0 $0

Project Details

Description
The purpose of this project is make improvements to the historic Quincy Loop station, including the addition of two elevators to make this station accessible. In addition, this project will repair, repaint and refinish interior elements throughout the stationhouse, and will also paint the exterior of the stationhouse. Lighting will be upgraded and the canopy roof will be repaired where necessary.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $650,000 $0 $0 $650,000

Last Updated 12.16.2022

+ Rail Station Communications Infrastructure Modernization Stations & Passenger Facilities Rail $5,000,000 $10,000,000

Project Details

Description
Project will provide for the comprehensive rehabilitation, overhaul, and expansion of communications infrastructure at all CTA rail stations to support new and modern technologies for customer facing as well as life safety functions. The rail station communications infrastructure upgrade will include the upgrade/rehabilitaion/expansion of communications infrasturcture at each rail station, including but not limted to conduit, cabling, power sources, networking, HVAC, grounding, and other ancillary physical infrastructure.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $5,000,000 $5,000,000 $10,000,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $75,004 $5,000,000 $5,000,000 $10,075,004

Last Updated 12.19.2024

+ Rail Station Customer Assistant Kiosk Security Consoles Stations & Passenger Facilities Rail $0 $0

Project Details

Description
Award provides for the initial installment of funds for phase one of a project that seeks to furnish a security video and communications console in every CTA rail station’s Customer Assistant Kiosk across the rail system. The first phase is targeting 50 CA kiosks at prioritized central business districts and high use rail stations.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $500,000 $0 $0 $500,000

Last Updated 12.19.2024

+ Rail Stations – Station Modernization Systemwide Stations & Passenger Facilities Rail $0 $37,700,000

Project Details

Description
Funding will provide for targeted station improvement program that provides for the repair or replacement of the following: signs, stairs, stainless steel handrails, stainless steel doors, flooring, ceiling, platform furniture refurbishment, LED lighting, tactile edge, wood platform, security fencing, and others. This work is beyond the Refresh and Renew program upgrades to stations.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $20,616,311 $20,616,311
State $0 $0 $17,083,689 $17,083,689
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $37,700,000 $37,700,000

Last Updated 12.19.2024

+ Refresh and Renew Program Expansion Stations & Passenger Facilities Rail $3,000,000 $6,000,000

Project Details

Description
Provides a heavy investment in refreshing stations and facilities every five years to promote safety, security and longevity to all CTA facilities including, but not limited to Rail Stations and Platforms, Bus Garages and Rail Shops across the system. The Refreshed & Renewed Program performs major improvement work at these transit operations facilities for both the customer and the internal needs of the Authority.Focus on the Customer experience, both internal and external.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $3,000,000 $3,000,000 $6,000,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $2,398,000 $3,000,000 $3,000,000 $8,398,000

Last Updated 12.19.2024

+ Rehabilitate Rail Stations - Systemwide Stations & Passenger Facilities Rail $0 $0

Project Details

Description
Rehabilitate Rail Stations Systemwide - Rail Stations Program would provide an annual appropriation for much-needed rehabilitation and modernization work at existing CTA rail stations. In addition, Infrastructure’s Rail Stations Program funds could be re-appropriated to support other critical needs at rail stations as they arise and implementation of systemwide projects can be scaled dependent on funding and locations.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $7,900,000 $0 $0 $7,900,000

Last Updated 12.16.2022

+ Rehabilitate Rail Stations -95th Terminal Stations & Passenger Facilities Rail $0 $0

Project Details

Description
This new job order will support the final change order for the construction firm, including the removal of several underground storage tanks near the terminal.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $9,000,000 $0 $0 $9,000,000

Last Updated 12.16.2022

+ Security Camera Modernization and Upgrade Stations & Passenger Facilities System $4,000,000 $7,568,629

Project Details

Description
Project will provide for the comprehensive overhaul of CTA's CCTV Security Camera Video System to upgrade the Authority's camera and video management system and communications transport system from antiquated and obsolete technology to modern high-speed technology with disaster recovery/business continuity solutions, increased capacity, and inter-operability with City of Chicago OEMC. The video system upgrade will include the upgrade of the master CCTV head-end system at the Control Center and Headquarters, and life safety CCTV systems upgrades at each rail station, transit facility, and critical infrastructure, with ancillary physical infrastructure.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $4,000,000 $2,379,629 $6,379,629
State $0 $0 $0 $0
RTA $0 $0 $1,189,000 $1,189,000
Service Board / Local $0 $0 $0 $0
Total $0 $4,000,000 $3,568,629 $7,568,629

Last Updated 12.19.2024

+ Systemwide Security Cameras Improvements (Safe & Secure) Stations & Passenger Facilities System $0 $0

Project Details

Description
Systemwide Security Cameras Improvements (Safe & Secure): Systemwide Security Cameras Safe and Secure investment of $18.0 M will add 1,000 new cameras and upgrade more than 3,800 older-model cameras throughout the system, including adding additional camera coverage to CTA-owned bus turnarounds and add monitors at all 146 CTA kiosks.$5M Modernize cameras$1M Install monitors at all kiosks$4M Install cameras at all CTA owned bus turnarounds$8M Maintain cameras in state of the art condition
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

Last Updated 12.16.2022

+ Western Station Brown Line - Reconstruction Stations & Passenger Facilities Rail $0 $0 ✔︎

Project Details

Description
Rehabilitation required at this station that was not part of the Brown Line Reconstruction project and has older elevators that are part of the ASAP program on replacing existing elevators.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $3,000,000 $0 $0 $3,000,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$33,487,325
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The contractor continued construction on the project. New electrical services were reviewed, revised, and advanced in the approval process. Construction activities during this reporting period focused on repair of the roof over the station lobby. The contractor will continue tuckpointing, demolition of the station ceiling, beautification of the Berlin Wall, and replacement of lighting on the walkway to Lincoln Avenue.

Last Updated 06.10.2025

+ Pace Fixed Route Buses - Replacement Bus $22,050,000 $24,276,820 $22,050,000 $0

Replacement of buses reaching useful life (CNG and OTR Coach).

Toggle Project Title Asset Category Mode 2025 Funding 2025-2029 Funding PMO
+ Fixed Route Hybrid Buses Rolling Stock Bus $9,600,000 $9,600,000 ✔︎

Project Details

Description
Replace diesel buses with 35-foot and 40-foot diesel-electric hybrid buses. This funding will allow Pace to transition to low-emission, cleaner vehicles, while the agency continues facility upgrades to accommodate ZEBs as part of the agency’s goal of operating a 100% ZEB fleet by 2040.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $9,600,000 $0 $9,600,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $90,443,261 $9,600,000 $0 $100,043,261

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$93,481,193
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Pace awarded the contractor for the purchase of the replacement and expansion 40FT hybrid-electric buses in October 2024. Pace finalized the projects delivery schedule with deliveries expected to start in July 2025 and final delivery in November 2025. The contract was executed in February 2025 for the purchase of thirty-three 35FT hybrid-electric buses. Pace met with the vendor to confirm the production and delivery schedule. The vendor confirmed that production of the buses is scheduled to start in Q1-2026 and final delivery expected in July 2026.

Last Updated 06.10.2025

+ Fixed Route OTR Coach Buses Rolling Stock Bus $12,450,000 $12,450,000

Project Details

Description
13 replacement OTR Coach buses including associated equipment (cameras, destination signs, etc.) and services (Buy America audit and inspections) for fixed route Bus on Shoulder services operating on I-55 out of Heritage Division in Plainfield.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $12,450,000 $0 $12,450,000
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $12,450,000 $0 $12,450,000

Last Updated 12.19.2024

+ Hydrogen Paratransit Vehicles Rolling Stock Bus $0 $2,226,820

Project Details

Description
6 expansion hydrogen fuel cell paratransit vehicles (cutaway) including associated equipment (cameras, destination signs, etc.), services (Buy America audit and inspections) and fueling trailer expenses for paratransit services operating as a demo pilot project out of Pace's River Division in Elgin.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $2,226,820 $2,226,820
Service Board / Local $0 $0 $0 $0
Total $0 $0 $2,226,820 $2,226,820

Last Updated 09.11.2025

+ Purchase 30' Diesel Buses Rolling Stock Bus $0 $0 ✔︎

Project Details

Description
This project is a new contract awarded in September 2019 for a new five?yearindefinite delivery/indefinite quantity contract for 30’ low floor diesel buses. Theminimum quantity to be purchased under this contract is 67 buses and the totalnumber of buses procured will not exceed the maximum amount of 164.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $9,096,667 $0 $0 $9,096,667

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$80,261,908
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
A total of 67 buses have been ordered to date. The first order consisted of 23 buses, all of which are in service. These were delayed due to the COVID-19 crisis. The second order consisted of 44 buses. All of the buses under the second order were received, with the final bus delivered in February 2023. The buses service the areas currently serviced by Fox Valley and Batavia. Pace will not pursue purchasing anymore buses under this contract. This will be the final update on this project.

Last Updated 04.01.2024