Project Management Oversight (PMO) Capital Projects
The RTA is responsible for ensuring that the Service Boards are spending capital funds and managing their capital projects effectively and efficiently. The RTA conducts periodic project reviews with Service Board project managers to ensure that capital projects are being implemented according to scope, on schedule, within budget and according to established project management guidelines.
Each project listed below is being actively monitored by RTA’s PMO team. Reporting data is provided that includes, Project Start Date, Project End Date, Budget Status, Schedule Status and Current Activities. These projects are also part of the overall Regional Capital Program which can be viewed separately here.
PMO also produces semi-annual reports that cover all projects that are being monitored. These reports can be found on the Project Management Oversight site. The latest report is the June 2025 Project Management Oversight report.
Search Capital Projects
| Toggle | Agency | Project Title | Asset Category | Mode | 2025 Funding | 2025-2029 Funding | Status | ||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| + | CTA | 2023 - Facilities Maintenance - Systemwide | Support Facilities & Equipment | System | $0 | $0 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
Maintenance Facilities Rehabilitation: Funding will be targeted at preventive maintenance projects at various CTA facilities systemwide. These projects will improve CTA's capacity to maintain stations and improve customer comfort and safety. CTA's Facilities department will identify stations for this targeted preventive maintenance work, driven by regular field audits performed by maintenance staff. Projects currently anticipated for this funding source may include leak remediation and grouting in stations; rehabilitation of CTA elevators and escalators (ADA); ceiling, roof or canopy repair / patching; lighting upgrades; painting and signage, among other items. This work will be performed by CTA maintenance forces with material procured as part of this project. Work will be conducted throughout the system and is considered routine preventive maintenance.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
Preventive maintenance reduces the occurrences of defects which occur as a result of water/snow, human error, leaks, asset wear and tear, and bearing failures. Facilities improvements were ongoing during this reporting period and maintenance work continues.
Last Updated 09.12.2025 |
|||||||||||||||||||||||||||||||||||||||||||||||
| + | CTA | 2024 - Elevated Track and Structure Maintenance Systemwide | Track & Structure | Rail | $0 | $0 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
Funding will be targeted at preventive maintenance projects for various Infrastructure units such as Track, Structure and Power. When certain maintenance tasks are needed to repair or replace asset components in order to maintain the working life of rail system, specific component campaign work is conducted. Capital maintenance work is targeted at the following areas: Elevated Track and Structure - repair/rehabilitate track and structure elements in order to eliminate slow zones and upgrade the right-of-way along the elevated structure throughout the rail system. Traction Power Substations - program that repairs and upgrades equipment at various traction power substations currently in service. Tactical upgrades correct deficiencies and avoid service reductions due to failure and overload of aging equipment. Third Rail and Heavy Traction Power Cables - Preventive maintenance work is performed where necessary to repair/replace heavy traction power cables that feed the third rail along the tracks currently in service at various locations throughout the rail system. Rail Signal Systems - Program provides for signal equipment repair along the rail right-of-way, signal equipment on rail cars, and the reconstruction of electronic components of the signal system, including relays and circuit boards. As necessary dedicated small renewals and system modifications are also completed. All work is planned/performed to maintain the asset(s) in proper working order through its quarter life cycle, while a more extensive rehabilitation is planned at the mid-life of the asset.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
Track and structure improvements continued during this reporting period. Major elements include, but are not limited to, ironworkers; track, signal and utilities work.
Last Updated 09.12.2025 |
|||||||||||||||||||||||||||||||||||||||||||||||
| + | Metra | A-20 (Techny) Interlocker | Electrical, Signal & Communications | Rail | $0 | $35,814,871 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
This project provides engineering and construction funds to modernize the A-20 Interlocking near Techny Road in Northbrook on the Milwaukee District North Line. The scope of work includes improving two grade crossings (Shermer and Techny Road), modernizing signals, and improving track between the Morton Grove Station and Deerfield Station. Under this project, work may include adding rail, switches, signals, crossovers, and renewal of track and signal circuits and cables. The project will implement a signal control system that is PTC compatible.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
Preliminary engineering work is near completion. Final design and materials solicitation package is ongoing. It will be submitted and advertised after the railroad cost sharing agreement is executed and potential grants are awarded.
Last Updated 06.10.2025 |
|||||||||||||||||||||||||||||||||||||||||||||||
| + | ADA Technology Upgrades and Transfer Centers | Systemwide | Bus | $0 | $0 | Behind Schedule | |||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
Regional ADA Paratransit Communication Technology and Transfer Locations - Projects include upgrades to the Trapeze software, TripCheck online booking and tracking, TripCheck Interactive Voice Response phone system, text/email notifications, and Ventra integration. In areas with frequent transfers, funding will be used to purchase land, build facilities, and provide amenities for riders. Pace has identified a location that is adjacent to the Northwest Transportation Center in Schaumburg that is planned to be the first of these transfer locations.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
Construction at the Northwest Transportation Center ADA Transfer Facility is ongoing and nearing completion. The contractor completed the transfer facility roof, resinous flooring, and installed restroom fixtures and toilets. The contractor started the installation of the monument signs.. The design for the Calumet City ADA transfer facility has reached the 90% milestone.
Pace implemented various technology enhancement projects. This portion of funding is mostly spent down. Final invoicing activities continue.
Last Updated 09.12.2025 |
|||||||||||||||||||||||||||||||||||||||||||||||
| + | CTA | All Station Accessibility Program & Canopies at Montrose | Stations & Passenger Facilities | Rail | $0 | $0 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
This job order will provide for the design/construction of two new elevators at the Montrose Blue Line Station. Further this project will fund replacement of canopies at Montrose station.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
This project is in the design phase. The 60% design has been reviewed by CTA. The State Historic Preservation Office (SHPO) also provided comments on the 60% design. The comments from CTA and SHPO will be incorporated into the 90% design. The design revisions and updates will need to be approved by SHPO at the 90% milestone. Coordination with ComEd for placement of transformers and switchgear utilities is ongoing.
Last Updated 06.10.2025 |
|||||||||||||||||||||||||||||||||||||||||||||||
| + | CTA | All Station Accessibility Program - Austin Station | Stations & Passenger Facilities | Rail | $0 | $0 | Behind Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
Rehabilitate Rail Stations - ASAP (AUSTIN): This project is part of CTA’s All Stations Accessibility Program (ASAP). The goal of ASAP is to create a vertically accessible rail system within 20 years. ASAP also adds accessibility features to vertically inaccessible stations such as sidewalks and crosswalks, power-assisted doors, accessible fare array, braille and signage, accessible Customer Assistance (CA) kiosks and staff toilet rooms, enhanced lighting as appropriate, and expanded platform clearances for wheelchair maneuverability.This project is to improve the vertical accessibility at the Lake Line Austin station (Austin station). The original street level station opened on April 15, 1899 as a section of the “Lake Street Elevated Railroad’s” surface level extension. The current stationhouse was rebuilt in 1962 as part of the project that moved the western end of the Lake Street line from a street level alignment to an abandoned strip of the parallel “Chicago and Northwestern Railway” embankment. The Lake Line began using this elevated right-of-way on the CN&W (today’s Union Pacific) embankment between Laramie and Harlem on Sunday, October 28, 1962. This station has not been upgraded since it was rebuilt. The Austin station has been identified as a station that is not vertically accessible for all customers and will require the installation of an elevator to serve this center platform configuration. Work on this project will also bring elements of the station up to current Chicago Building Code requirements and meet the National Fire Protection Association (NFPA) 130 Standard for Fixed Guideway Transit and Passenger Rail Systems emergency egress requirements.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
Construction activities are ongoing. During this reporting period, a soft opening occurred at Mason Stationhouse on Monday, July 14, 2025, with Austin Stationhouse closing. Additional fare control equipment was installed at Mason Stationhouse prior to the closure to accommodate ridership. CTA Signage Department worked it the Engineering group to have the required passenger notification signs in place prior to closure. CTA Government and Community Relations ensured that customer announcement notification (CAN) signs were in place to lead customers to the Mason Stationhouse. Construction activities continue.
Last Updated 09.12.2025 |
|||||||||||||||||||||||||||||||||||||||||||||||
| + | CTA | All Stations Accessibility Program - Irving Park and Belmont Station | Stations & Passenger Facilities | Rail | $0 | $0 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
Irving Park and Belmont - O’Hare Blue accessibility enhancments including new elevators.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
This project is in the design phase. CTA issued a Notice to Proceed to the designer in April 2025. A kickoff meeting was held, and design activities are in the preliminary stages. CTA is working on the National Environmental Policy Act (NEPA) process for this project.
Last Updated 06.10.2025 |
|||||||||||||||||||||||||||||||||||||||||||||||
| + | Metra | Auburn Park New Station | Stations & Passenger Facilities | Rail | $0 | $0 | Behind Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
The new station in the Auburn Park neighborhood of Chicago will feature a platform-length canopy and heated headhouse with two elevators. The station will include a center boarding platform with a staircase down to street level entrance tunnel, a landscaped plaza with benches, canopy, bicycle parking, and a vendor space Metra will lease. A parking lot will include 79 parking stalls, 5 ADA parking spaces, and a passenger drop-off lane. The new station will be fully ADA accessible.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
The construction activities are in progress. Construction work during this reporting period focused on removing the track level ramp at track crossing, sub-ballast layer installation and compaction, and preparing and waterproofing bridge deck. The contractor also completed electrical branch and duct bank work at the transformer.
Last Updated 09.12.2025 |
|||||||||||||||||||||||||||||||||||||||||||||||
| + | Metra | Bicycle Parking | Stations & Passenger Facilities | Rail | $0 | $0 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
Metra was awarded CMAQ grants for the purchase and installation of bicycle parking facilities at stations across the system. Specific locations are to be determined
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
Metra reached the 100% design submittal which is ongoing due to scope changes. Three stations were added to the scope of this project. The designs were completed, and Metra will proceed to begin the procurement process for construction as well as construction management services.
Last Updated 09.12.2025 |
|||||||||||||||||||||||||||||||||||||||||||||||
| + | CTA | Blue Line O'Hare Branch Traction Power Improvements | Track & Structure | Rail | $0 | $0 | On Schedule | ||||||||||||||||||||||||||||||||||||||||
Project DetailsDescription
Blue Line O'Hare Branch Traction Power Improvements GTT - Project will include targeted track repairs to remove existing slow zones on the Congress Branch of the Blue Line. CTA has identified traction power voltage drop issues along the Blue Line. Scope of work will include but not limited to the following elements: New infill substations, infill wayside energy storage systems, infill tie houses, third rail replacement, addition of auxiliary negative rail; work will be performed by an outside contractor. In addition project will aslo provide for the replacement of ties, track fasteners, footwalks, and incidental signal and traction power; this part of work will be performed by CTA Field Forces.
Capital Evaluation Metrics
Click here to view the projects capital evaluation metrics
Funding Amounts by Source
PMO:
^Total Project Budget is the project budget being tracked by the RTA PMO Group Current Status
The contractor completed installation and testing of wayside signal equipment and all cutovers along the specific portion of the blue line. The project is considered substantially complete with the contractor performing punch list items. Final invoices remain and this will be the final update on this project.
Last Updated 06.22.2023 |
|||||||||||||||||||||||||||||||||||||||||||||||