Project Management Oversight (PMO) Capital Projects

The RTA is responsible for ensuring that the Service Boards are spending capital funds and managing their capital projects effectively and efficiently.  The RTA conducts periodic project reviews with Service Board project managers to ensure that capital projects are being implemented according to scope, on schedule, within budget and according to established project management guidelines.

Each project listed below is being actively monitored by RTA’s PMO team. Reporting data is provided that includes, Project Start Date, Project End Date, Budget Status, Schedule Status and Current Activities. These projects are also part of the overall Regional Capital Program which can be viewed separately here.

PMO also produces semi-annual reports that cover all projects that are being monitored. These reports can be found on the Project Management Oversight site. The latest report is the June 2025 Project Management Oversight report. 

Search Capital Projects

i

This search filters based on details within the PMO Project. The search box below allows users to search by PMO Project name.

Toggle Agency Project Title Asset Category Mode 2025 Funding 2025-2029 Funding Status
+ Metra Substation Improvements - Matteson Substation Support Facilities & Equipment Rail $0 $0 Behind Schedule

Project Details

Description
This project is for the replacement of the rectifiers at substations along the Metra Electric Line. The rectifiers are 35 years old and they have long exceeded their useful life. Replacement parts are not available. The Matteson Substation has been identified as a high priority location. Planned work at Matteson includes construction services to replace and add traction power equipment including a 15kv AC switchgear lineup and two?dry type copper?winding traction power transformers. Other locations identifed under this project include Jackson Substation and Homewood Substation.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $0 $0 $0 $0

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$15,360,209
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The Contractor continues to perform mechanical field testing for the substation. Procurement of long lead time items such as transfer switches and switch gears is ongoing. Construction activities continue.

Last Updated 09.12.2025

+ CTA Tactical Traction Power (Equipment/Cable/Enclosures) Track & Structure Rail $0 $0 On Schedule

Project Details

Description
State of Good Repair projects and replacing obsolete equipment on CTA rail signal system
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $1,550,000 $0 $0 $1,550,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$10,293,685
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The General Contractor completed construction activities and reached substantial completion during this reporting period. The contractor continues with punch list and closeout activities and final invoices remain. This will be the final update on this project.

Last Updated 06.10.2025

+ Metra Ticket Vending Machines Stations & Passenger Facilities Rail $0 $0 On Schedule

Project Details

Description
This project is the first phase of installing up to 310 ticket vending machines (TVMs) at selected stations throughout the Metra system to provide added amenities to Metra customers. The TVMs will offer a variety of ticket purchasing options and make purchasing tickets faster, easier, and more convenient for our customers. The TVMs will be fully ADA-accessible and will offer the ability to purchase tickets using contactless cards and mobile wallet applications and will no longer need to insert debit/credit cards into the machine.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $38,160,000 $0 $0 $38,160,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$35,290,090
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
This project is currently in the production phase. Construction, delivery, and installation of the Ticket Vending Machines is in progress. A total of 270 machines have been installed.

Last Updated 09.12.2025

+ Metra Ties & Ballast MED Track & Structure Rail $0 $0 On Schedule

Project Details

Description
These projects consist of the replacement of cross ties, switch ties and ballast. In order to maintain proper track gauge and surface, it is necessary to replace ties and ballast periodically. This improves the riding quality of the trains and reduces the incidence of slow orders, which adversely affect adherence to train schedules. These projects represent part of an ongoing program to replace ties and ballast throughout the commuter territory.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $13,446,000 $0 $0 $13,446,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$4,100,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Major elements for this project included ironworkers; track, signal and utilities work. Track and structure improvements were completed during this reporting period and final invoices remain. This will be the final update on this project.

Last Updated 04.01.2024

+ Metra Ties & Ballast MWD-W Track & Structure Rail $0 $0 On Schedule

Project Details

Description
Metra’s track renewal crew will rehabilitate dozens of miles of track along the Milwaukee District West (MD-W) Line in 2022. The project will be the most comprehensive investment in track conditions since Metra acquired the MD-W in 1987. Metra forces will Replace ties, clean or replace ballast, and replace switch components to provide smoother, faster, and safer track conditions. Metra partners with the Canadian Pacific Railroad to fund improvements to particular portions of the MD-W as freight train traffic degrade track conditions more rapidly than Metra trains.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $18,487,855 $0 $0 $18,487,855

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$4,331,634
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Track and structure improvements were completed during this reporting period. Major elements include ironworkers; track, signal and utilities work. This will be the final update on this project.

Last Updated 06.10.2024

+ Metra Ties & Ballast RID Track & Structure Rail $0 $0 On Schedule

Project Details

Description
These projects consist of the replacement of cross ties, switch ties and ballast. In order to maintain proper track gauge and surface, it is necessary to replace ties and ballast periodically. This improves the riding quality of the trains and reduces the incidence of slow orders, which adversely affect adherence to train schedules. These projects represent part of an ongoing program to replace ties and ballast throughout the Rock Island District.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $7,520,000 $0 $0 $7,520,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$1,920,000
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
Major elements for this project includes ironworkers; track, signal and utilities work. Track and structure improvements completed during this reporting period. This will be the final update on this project.

Last Updated 06.10.2024

+ CTA Traction Power Upgrades - Kedvale, Edmunds & Sacramento Substations Track & Structure Rail $0 $0 On Schedule

Project Details

Description
This project will Provide for AC breaker replacement at Kedvale, Edmunds and Sacramento substations. This will also include the replacement of oil (non?PCB) transformer and rectifiers along with roof and doors replacement at the Kedvale and Sacramento substations.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $18,586,628 $0 $0 $18,586,628

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$12,030,427
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The contractor was able to install the transformers, rectifiers, as well as roof and door replacements since the last reporting period. The project reachedsubstantial completion in January 2023 and punchlist items were completed. Final invoices remain. This will be the final update on this project.

Last Updated 06.22.2023

+ Pace Transit Signal Priority (TSP) Electrical, Signal & Communications Bus $0 $0 On Schedule

Project Details

Description
Transit Signal Priority Integration - TSP implementation along priority corridors as part of the Regional Transit Signal Priority Implementation Program. Pace plans to deploy TSP along nine additional corridors at approximately 300 signalized intersections. The corridors include: 159th Street, Sibley Boulevard/147th Street, Roosevelt Road, Cicero Avenue, 95th Street, Grand Avenue (Lake County), Cermak Road, I-90 Transit Corridor Access Intersections and Halsted Street. This form represents the portion of the project funded with PAYGO in 2024. Years 2021-2023 of TSP related projects are funded with ICE funds as shown in Exhibit I.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $2,975,000 $0 $0 $2,975,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$14,031,402
On Budget
On Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
TSP system integration and testing continued across multiple corridors. On Dempster Street, systems integration and TSP testing are complete. Grand Ave. has completed systems integration, with testing ongoing. Roosevelt Rd. and 147th Street have completed testing, with systems integration and data review continuing. Integration and testing are ongoing along 95th Street and Cicero Ave. Mobilization efforts continue for Cermak and Rand corridors, with permitting progress reported. Permit acquisition from IDOT is complete for 159th, and the vendor is finalizing bond and insurance requirements.

Last Updated 06.10.2025

+ Metra Union Pacific West Line Expansion Track & Structure Rail $0 $0 Behind Schedule

Project Details

Description
This project, a Public-Private Partnership between Metra and the Union Pacific Railroad, will construct two new segments of third mainline track on the Union Pacific West Line. One of the segments will be between the Vale Interlocking at milepost 10.0 in River Forest and the 25th Avenue Interlocking at milepost 11.8 in Melrose Park. The other segment will be between the Kress Interlocking at milepost 32.1 in West Chicago and the Peck Interlocking at milepost 38.4 in Geneva. Improvements are anticipated for all four of the interlockers that bookend the two segments. Additionally, a new interlocker may be constructed at milepost 35.4 between the Kress and Peck interlockers, which will increase operational flexibility. The interlocker improvements and additions will be constructed to meet Positive Train Control requirements. Improvements along both segments will include, but not be limited to, trackwork, earthwork, sub-ballast, structures, signal infrastructure, interlocking upgrades, and all work necessary at highway grade crossings. Bridge improvements will be needed over both the Des Plaines River and the Fox River to allow for the third mainline track. The project will also include platform relocations and improvements at both the Maywood and Melrose Park stations, and platform, platform shelter, and parking improvements at the Geneva station. Lastly, land acquisition may be required at various locations along the two segments in areas where the right of way is not wide enough to accommodate the third main track within the track centers required by the Union Pacific.
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $50,000 $0 $0 $50,000

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$127,477,280
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
This project has reached substantial completion. The RTA PMO team performed a final walk through in May 2025. This will be the last report on this project.

Last Updated 06.10.2025

+ Metra UP North Line - North 11 Bridges and Ravenswood Station Track & Structure Rail $0 $0 Behind Schedule

Project Details

Description
This project involves the replacement of 22 bridges on the UP North Line in Chicago, Illinois. The structural scope of work will include, but not be limited to, replacement of existing stone abutments, retaining wall construction, steel spans, and decks. Also, some track work will be accomplished between the bridges, including the replacement of wood ties with concrete ties, and some commuter station modifications will be required, including the Ravenswood Station. To ensure reliable train operations, theproject will include various signal improvements, including: new interlockers at Addison Street (MP 5.0) and Rosehill (MP 7.3, between Balmoral Avenue and Bryn Mawr Avenue), and upgrades to the Deering interlocker (MP 3.2). In
Funding Amounts by Source
*Previous funding shows all funding since 2020, but not with detail by funding source. Note that the project may have funding from capital programs previous to 2020 that is not shown in table.
Source Previous Funding* 2025 Funding 2026-2029 Funding Total
Federal $0 $0 $0 $0
State $0 $0 $0 $0
RTA $0 $0 $0 $0
Service Board / Local $0 $0 $0 $0
Total $983,006 $0 $0 $983,006

PMO:

Total Project Budget^ Budget Status Schedule Status Start Date End Date
$50,255,463
On Budget
Behind Schedule

^Total Project Budget is the project budget being tracked by the RTA PMO Group

Current Status
The bridge construction has been completed in September 2021. The station contractor reached substantial completion in August 2023. The contractor continues to address punch list items on the station. The station had a soft opening at the beginning of August and its opening ceremony at the beginning of October. This will be the final update of this project.

Last Updated 12.14.2023